Pool Project 2008
A,View Creek Side for web 800X33906

CREEKSIDE CROSSING
Pelican Landing        Bonita Springs, Florida

     Calendar of Events     Fall PICTURES 2008         Pool Project 2008                            

MAY 15TH

THE RESURFACING OF THE TWO POOLS STARTED WITH THE NORTH POOL. THE FOLLOWING DISCRIPTIONS AND PICTURES ARE VIA EMAILS FROM HANK MAIER.

The work has started. As you can see the pool is empty and it only took a couple of hours for the two pumps to do the job.  After it was empty they took a steel rod and punched about four holes in the bottom of drain well so that water could drain out or up if there was excessive pressure in the water table.  Excessive rain at this point is their worst enemy. 

You will notice the coping was removed in two places. These are areas where the tile had popped before. Well the thick bed of mortar they used to set the tiles was only a bandaid. Their contention is that using a layer of then-set which will be much thinner is the correct way to set the tile........being the active foreman on the job, I concur.

Another surprise, when they removed one of the ceramic bullnose from the steps there was another one under it.  This means that this set of steps was done  twice.  The team of workers that are there now do all the prep work. Removing all the tile and the final coat which can be from 1" to 3+" thick, then and acid wash it followed by a prep coat.  Then comes the next team, the finishers.

The committee who picked Penguin Pools is to be commended.

Hank

DSC01995 for web DSC02001 for web
DSC01998 for web DSC02000 for web
DSC02006 for web
DSC02007 for web

MAY 20

THE FOLLOWING PICTURES AND INFORMATION WERE PROVIDED BY TED SMITH

The north pool is almost finished with the removal of the pool liner. It has been a hot, dusty job, but the workmen seem to be good. They were not there today but will have a crew tomorrow for cleanup, etc. The coping has been measured and ordered. It generally takes two weeks to have coping delivered but Penguin is trying to rush the order. The drains have to be chipped out and the holes have to be filled behind the coping.  I am attaching 4 additional pics of the pool and a pic of the pipe that burst

 

DSCN0194 for web02
DSCN0193 for web04
DSCN0195 for web02
DSCN0196 for web02
DSCN0199 for web02

MAY 28

Even though the demolition is not 100% complete, work has begun on the reconstruction of the pool.  The second phase will start from the top down. Starting with the coping, then the 6" x 6" tile below the coping and the final finish coat which I, like everyone else in CSC, are looking forward to seeing.  The pictures show how the gauged coat is applied for the Coping.  All but 15' was finished today.  According to John, the one in charge of this crew, the target date for setting the coping should hopefully be Mon. 6/2/08
Hot Wheels Hank

 

DSC02055 for web
DSC02053 for web
DSC02056 for web
DSC02060 for web
DSC02062 for web
DSC02064 for web

JUNE 2

REVISED SCHEDULE AS PROVIDED BY STEVE ALLEN FROM PEGASUS

                          JUNE 6                     COPING AND TILE TO BE COMPLETED
                               JUNE 13                  LINER FINISHED AND POOL REFILLED
                               JUNE 18                  POOL READY FOR USE
                               JUNE 19                  DEMOLITION OF SOUTH
POOL

 

JUNE 7

The new coping has been placed, but is not yet completed because some had to be redone to fit correctly. R.D. Boschulte

IMG_0027[2] for web
IMG_0029 for web

JUNE 13

The following pictures,taken by R.D. Boschulte, show the new tile below the coping.  The project foreman feels that most of the work on the south pool will be completed by June 18th or 19th.

IMG_0036 for web02
IMG_0037 for web02
IMG_0038 for web02
IMG_0040for web02

    JUNE 21

The birdseye view of the completed north pool is already 60% filled with water. It won’t be long before it will be in use.  This picture was taken by
 R.D. Boschulte.

 

IMG_0046 for web

Demolition of the south pool will begin as soon as the north pool is ready for use. The process to completion will be the same as was used on the north pool.  The only difference will be the addition of a second hand rail on the south steps entering the  pool.

PROJECT COMPLETED

Hot Tub for Web03

HOT TUB

South Pool for Web
South Pool Main steps for web 3

SOUTH POOL

BuiltWithNOF

WITH TWO HAND RAILS ON ENTRANCE STEPS